BTC - Additional Facilities and Ankara Offices
Baku Tblisi Ceyhan Pipeline - Pumping and Pressure Regulation Stations (PT-1, PT-2, PT-3, PT-4, IPT-1, IPT-2), Haydar Aliyev Seaport (CMT) Additional Facilities and Ankara Office

119 structures across 8 locations
About the Project
The project spans across 8 key operational facilities located in Adana, Kahramanmaraş, Sivas, Erzincan, Erzurum, Kars, Ardahan, and Ankara
Responsibilities & Key Obligations
Turnkey Delivery: Responsible for completing all civil, architectural, structural (reinforced concrete and steel), mechanical, and electrical works fully functioning and complying with the highest quality standards and Turkish/International norms (TSE, ISO, DIN, VDE, NFPA, ASHRAE).
Permits & Legalities: Securing all municipal building permits (yapı ruhsatı) and occupancy permits (iskan ruhsatı), along with utility subscriptions (electricity, water, telecom, natural gas).
Advanced Monitoring Systems: Deploying digital site tracking technologies, including Unmanned Aerial Vehicles (UAVs / Drones) for orthophoto mapping every 15 days, AI-supported video analytics for progress tracking, vehicle logging, worker headcounts, and 24/7 security camera streaming.
Key Special Provisions
PT2 Winter/Spring Measures: Special precautions must be taken at the PT2 station against potential spring flooding during construction.
IPT1 Camp Relocation: Relocation and re-installation of 76 existing operational structures (mostly containers and prefab units) at IPT1 to a designated BIL area.
KASKI Pipeline Relocation: Relocation of two 750-meter long, 280 mm diameter PE water pipelines belonging to KASKI at the IPT1 camp area.
CMT Prefabricated Office: Demolition of the existing 650 m² prefab office and construction of a new equivalent facility before dismantling the old structure.